Topic 1, Volume A
Configuration identification, configuration status accounting, and configuration verification and
audit are all activities in which process?
A.
Perform Quality Assurance
B.
Direct and Manage Project Work
C.
Monitor and Control Project Work
D.
Perform Integrated Change Control
Perform Integrated Change Control
Which tool or technique is used in the Estimate Costs process?
A.
Acquisition
B.
Earned value management
C.
Vendor bid analysis
D.
Forecasting
Vendor bid analysis
Which type of project management office (PMO) supplies templates, best practices, and training to
project teams?
A.
Supportive
B.
Directive
C.
Controlling
D.
Instructive
Supportive
Which Define Activities output extends the description of the activity by identifying the multiple
components associated with each activity?
A.
Project document updates
B.
Activity list
C.
Activity attributes
D.
Project calendars
Activity attributes
An input to the Identify Stakeholders process is:
A.
The project management plan.
B.
The stakeholder register.
C.
Procurement documents.
D.
Stakeholder analysis.
Procurement documents.
Page 28 out of 157 Pages |